Stornoway Announces Advanced Renard Construction Schedule With Reduced Cost to Complete Forecast

LONGUEUIL, Quebec, Feb. 03, 2016 (GLOBE NEWSWIRE) -- Stornoway Diamond Corporation (TSX:SWY) (the “Corporation” or “Stornoway”) is pleased to announce a revised construction schedule for the Renard Diamond Project with an associated reduction in the forecast cost to complete. Re-baselining of the project’s schedule and capital cost forecasts has been made possible following several months of construction progress achieved consistently ahead of plan, and has been undertaken as part of the revised mine planning for Renard which is expected to be completed in the second quarter of this year.

First ore delivery to the Renard diamond process plant has now been scheduled for the end of September 2016, with commercial production (60% of plant capacity achieved over 30 days) to be achieved by December 31, 2016. This is a 5 month improvement on the previous schedule, which assumed commercial production in the second quarter of 2017.

The estimated capital cost to complete for the project has been adjusted downwards from C$811.0 million to C$775.4 million, reflecting savings in general and administrative expenses and capitalized operating expenses. The new cost forecast includes all contingencies, escalation allowances, and working capital up to the date of commercial production.

Matt Manson, President and CEO, commented, “This improvement in our development schedule at Renard has been made possible by the excellent construction environment we are enjoying in Québec and the efficient progress made by our team. The reduced cost to complete adds further strength to our balance sheet, already boosted by the ongoing F/X gains on the portion of our project financing that was funded or committed in US$. Future progress reporting at Renard will be with reference to these re-baselined schedule and cost targets.”

As of December 31st, 2015, prior to the re-baselining exercise, overall construction at the project stood at 63.3% compared to a plan of 59.6%, with engineering substantially complete at 99.0%. An updated mine plan for the Renard Project is under preparation and is expected to be released early in the second quarter of this year. This plan will incorporate the re-baselined schedule and capital cost for the construction of the project, and will include revised guidance on production profile, mine life, operating costs, sustaining capital and Mineral Reserves. This work is currently ongoing.

About the Renard Diamond Project

The Renard Diamond Project is located approximately 250 km north of the Cree community of Mistissini and 350 km north of Chibougamau in the James Bay region of north-central Québec. On July 8th 2014 Stornoway announced the completion of a C$946 million project financing transaction to fully fund the project to production, and construction commenced on July 10th, 2014. First ore is scheduled to be delivered to the plant at the end of September 2016, with commercial production scheduled for December 31, 2016.

In January 2013, Stornoway released the results of an Optimized Feasibility Study at Renard which highlighted the potential of the project to become a significant producer of high value rough diamonds over a long mine life. Probable Mineral Reserves, as defined in National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”), stand at 17.9 million carats. In accordance with the Corporation’s September 2015 Mineral Resource estimate, total Indicated Mineral Resources, inclusive of the Mineral Reserve, stand at 30.2 million carats, with a further 13.35 million carats classified as Inferred Mineral Resources, and 33.0 to 71.1 million carats classified as non-resource exploration upside.  Average annual diamond production is forecast at 1.6mcarats/year over the first 11 years of mining, at an average valuation of US$190/carat based on a March 2014 assessment by WWW International Diamond Consultants Ltd.

Readers are cautioned that the potential quality and grade of any target for further exploration is conceptual in nature, there has been insufficient exploration to define a Mineral Resource and it is uncertain if further exploration will result in the target being delineated as a Mineral Resource. All kimberlites remain open at depth. Readers are referred to the technical report dated February 28th, 2013 in respect of the January 2013 Optimization Study, and the technical report dated January 11, 2016 in respect of the September 2015 Mineral Resource estimate, for further details and assumptions relating to the project. Disclosure of a scientific or technical nature in this press release was prepared under the supervision of Patrick Godin, P.Eng. (Québec), Chief Operating Officer and Robin Hopkins, P.Geol. (NT/NU), Vice President, Exploration, both Qualified Persons (“QP”) under National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).

About Stornoway Diamond Corporation

Stornoway is a leading Canadian diamond exploration and development company listed on the Toronto Stock Exchange under the symbol SWY and headquartered in Montreal. Our flagship asset is the 100% owned Renard Diamond Project, on track to becoming Québec’s first diamond mine. Stornoway is a growth oriented company with a world class asset, in one of the world’s best mining jurisdictions, in one of the world’s great mining businesses.

On behalf of the Board
STORNOWAY DIAMOND CORPORATION
/s/ “Matt Manson”
Matt Manson
President and Chief Executive

For more information, please contact Matt Manson (President and CEO) at 416-304-1026 x2101
or Orin Baranowsky (Director, Investor Relations) at 416-304-1026 x2103
or toll free at 1-877-331-2232

Pour plus d’information, veuillez contacter M. Ghislain Poirier, Vice-président Affaires publiques de Stornoway au 418-254-6550, gpoirier@stornowaydiamonds.com

** Website: www.stornowaydiamonds.com Email: info@stornowaydiamonds.com **

This press release contains "forward-looking information" within the meaning of Canadian securities legislation. This information and these statements, referred to herein as “forward-looking statements”, are made as of the date of this press release and the Corporation does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by law.

These forward-looking statements include, among others, statements with respect to Stornoway’s objectives for the ensuing year, Stornoway’s medium and long-term goals, and strategies to achieve those objectives and goals, as well as statements with respect to Stornoway’s beliefs, plans, objectives, expectations, anticipations, estimates and intentions. Although management considers these assumptions to be reasonable based on information currently available to it, they may prove to be incorrect.

Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: (i) the amount of Mineral Resources and exploration targets; (ii) the amount of future production over any period; (iii) net present value and internal rates of return of the mining operation; (iv) assumptions relating to recovered grade, average ore recovery, internal dilution, mining dilution and other mining parameters set out in the 2011 Feasibility Study or the Optimization Study; (v) assumptions relating to gross revenues, operating cash flow and other revenue metrics set out in the 2011 Feasibility Study or the Optimization Study; (vi) mine expansion potential and expected mine life; (vii) expected time frames for completion of permitting and regulatory approvals related to construction activities at the Renard Diamond Project; (viii)  the expected time frames for the completion of the open pit and underground mine at the Renard Diamond Project; (ix) the expected time frames for the completion of construction, start of mining and commercial production at the Renard Diamond Project and the financial obligations or costs incurred by Stornoway in connection with such mine development; (x) future exploration plans; (xi) future market prices for rough diamonds; (xii) the economic benefits of using liquefied natural gas rather than diesel for power generation; (xiii) sources of and anticipated financing requirements; (xiv) the effectiveness, funding or availability, as the case may require, of the Stream, the Senior Secured Loan, the COFand the Equipment Facility and the use of proceeds therefrom; (xv) the Corporation’s expectations regarding receipt of the remaining deposits under the Stream and its ability to meet its delivery obligations thereunder; (xvi) the impact of the Financing Transactions on the Corporation’s operations, infrastructure, opportunities, financial condition, access to capital and overall strategy;  (xvii) the foreign exchange rate between the US dollar and the Canadian dollar; and (xviii) the availability of excess funding for the construction and operation of the Renard Diamond Project . Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as “expects”, “anticipates”, “plans”, “projects”, “estimates”, “assumes”, “intends”, “strategy”, “goals”, “objectives”, “schedule” or variations thereof or stating that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements are made based upon certain assumptions by Stornoway or its consultants and other important factors that, if untrue, could cause the actual results, performances or achievements of Stornoway to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business prospects and strategies and the environment in which Stornoway will operate in the future, including the price of diamonds, anticipated costs and Stornoway’s ability to achieve its goals, anticipated financial performance, regulatory developments, development plans, exploration, development and mining activities and commitments, and the foreign exchange rate between the US and Canadian dollars. Although management considers its assumptions on such matters to be reasonable based on information currently available to it, they may prove to be incorrect. Certain important assumptions by Stornoway or its consultants in making forward-looking statements include, but are not limited to: (i) required capital investment and estimated workforce requirements; (ii) estimates of net present value and internal rates of return; (iii) receipt of regulatory approvals on acceptable terms within commonly experienced time frames; (iv) anticipated timelines for completion of construction, commencement of mine production and development of an open pit and underground mine at the Renard Diamond Project, which heavily depend, among other things, on adequate availability and performance of skilled labour, engineering and construction personnel, performance of mining and construction equipment and timely delivery of components;‎ (v) anticipated geological formations; (vi) market prices for rough diamonds and the potential impact on the Renard Diamond Project; (vii) the satisfaction or waiver of all conditions under each of the Stream, the Senior Secured Loan, the COF and the Equipment Facility to allow the Corporation to draw on the funding available under those financing elements for the completion of the development and construction of the Renard Diamond Project; (viii) Stornoway’s interpretation of the geological drill data collected and its potential impact on stated Mineral Resources and mine life; (ix) future exploration plans and objectives; (x) the receipt of the remaining deposits under the Stream and the Corporation’s ability to meet its delivery obligations thereunder; and (xi) the continued strength of the US dollar against the Canadian dollar. Additional risks are described in Stornoway's most recently filed Annual Information Form, annual and interim MD&A, and other disclosure documents available under the Corporation’s profile at: www.sedar.com.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward- looking statements as a number of important risk factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements. These risk factors may be generally stated as the risk that the assumptions and estimates expressed above do not occur, including the assumption in many forward-looking statements that other forward-looking statements will be correct, but specifically include, without limitation: (i) risks relating to variations in the grade, kimberlite lithologies and country rock content within the material identified as Mineral Resources from that predicted; (ii) variations in rates of recovery and breakage; (iii) the uncertainty as to whether further exploration of exploration targets will result in the targets being delineated as Mineral Resources; (iv) developments in world diamond markets; (v) slower increases in diamond valuations than assumed; (vi) risks relating to fluctuations in the Canadian dollar and other currencies relative to the US dollar; (vii) increases in the costs of proposed capital and operating expenditures; (viii) increases in financing costs or adverse changes to the terms of available financing, if any; (ix) tax rates or royalties being greater than assumed; (x) uncertainty of results of exploration in areas of potential expansion of resources; (xi) changes in development or mining plans due to changes in other factors or exploration results; (xii) changes in project parameters as plans continue to be refined; (xiii) risks relating to the receipt of regulatory approvals or the implementation of the existing Impact and Benefits Agreement with aboriginal communities; (xiv) the effects of competition in the markets in which Stornoway operates; (xv) operational and infrastructure risks; (xvi) execution risk relating to the development of an operating mine at the Renard Diamond Project; (xvii) failure to satisfy the conditions to the effectiveness, funding or availability, as the case may require, of each of the Stream, the Senior Secured Loan, the COF and the Equipment Facility; (xviii) changes in the terms of the Stream, the Senior Secured Loan, the COF or the Equipment Facility; (xix) the funds of the Stream, the Senior Secured Loan, the COF or the Equipment Facility not being available to the Corporation; (xx) the Corporation being unable to meet its delivery obligations under the Stream; (xxi) future sales or issuances of Common Shares lowering the Common Share price and diluting the interest of existing shareholders;  and (xxi) the additional risks described in Stornoway's most recently filed Annual Information Form, annual and interim MD&A and Stornoway's anticipation of and success in managing the foregoing risks. Stornoway cautions that the foregoing list of factors that may affect future results is not exhaustive, and new, unforeseeable risks may arise from time to time.

 


Source: GlobeNewswire (February 3, 2016 - 7:00 AM EST)