Yesterday Cheniere Energy, Inc. (stock ticker: LNG), in partnership with privately-held Bechtel, produced the first LNG from the Corpus Christi Liquefaction project (CCL Project) in Texas.

According to a 3Q 2018 presentation by Cheniere, the CCL Project is the first greenfield LNG export facility in the U.S. Lower-48. There are three trains, with 13.5 mtpa total capacity.

Train 1 has finished construction, and has been undergoing commissioning, with completion expected Q1 2019. Feed gas was introduced in August 2018.
Train 2 is under construction with completion expected 2H 2019.
Train 3’s FID was in May 2018, with substantial completion expected 2H 2021.

Source: Cheniere

Cheniere’s CCL Project is being developed in stag...