Tellurian Inc. (ticker: TELL) announced today that the Federal Energy Regulatory Commission (FERC) has issued the notice of schedule for environmental review of Driftwood LNG, a proposed 27.6 million tonnes per annum (mtpa) liquefied natural gas (LNG) export facility, and Driftwood Pipeline, a proposed 96-mile, 4 billion cubic feet a day (Bcf/d) pipeline.

According to the notice, FERC will issue its final Environmental Impact Statement (EIS) on October 12, 2018, and has established a 90-day Federal Authorization Decision Deadline on January 10, 2019. Assuming a favorable decision, Tellurian expects that this schedule will allow it to begin construction of Driftwood LNG in early 2019, pending a final investment decision by Tellurian.

 

Estimated Driftwood Project timeline
Catalyst Estimated timeline
Driftwood commercial agreements 1H 2018
Draft Environmental Impact Statement 1H 2018
Final Environmental Impact Statement 12 October 2018
FERC order and Federal Authorization Deadline 10 January 2019
Driftwood final investment decision 1H 2019
Begin construction 1H 2019
Begin operations 2023

 